Sanitaryware Installation

Sanitary Ware Installation Guide

1. General Installation Preparation

  • Check all items for cracks, glaze defects, or missing accessories before installation.
  • Keep installation manuals or templates ready.
  • Use only recommended grade sanitary silicone, anchor bolts, and thread sealants.
  • Ensure plumbing lines are flushed before connecting sanitaryware.

2. Wash Basin Installation

Type Key Steps
Wall-Hung Basin
  • Use wall template to mark bolt holes
  • Drill & fix anchor bolts securely
  • Seal back with silicone, connect waste & tap
Countertop Basin
  • Cut counter as per basin shape
  • Apply silicone below basin rim
  • Connect waste & tap above counter
Pedestal Basin
  • Fix basin to wall and rest on pedestal
  • Hide pipework inside pedestal
  • Seal contact points with silicone
  • Always ensure height from finished floor = 800–850 mm for user comfort.

3. Water Closet (WC) Installation

Type Key Steps
Floor-Mounted (S-trap / P-trap)
  • Place on setout point using manufacturer's template
  • Fix using anchor bolts or cement-based adhesive
  • Connect to waste pipe with sealing ring
  • Apply silicone around base
Wall-Hung WC
  • Ensure concealed tank is installed & tested before fixing WC
  • Mark bolt points, fix WC on wall carrier frame
  • Tighten bolts, connect flush pipe & waste outlet
  • Test flush before sealing with silicone
  • Standard height from floor to top rim (WC): 400–430 mm
  • For western toilets, test both flush performance and water seal depth.

4. Urinal Installation

  • Install urinal brackets or frame at recommended height
  • Connect flush inlet and drain outlet.
  • Apply silicone around edges
  • Optional: install urinal partition walls for public use

Ideal height from floor to urinal lip:

  • Men : 610–650 mm
  • Boys: 350–450 mm

5. Silicone Sealing & Final Finishing

  • Use non-staining, waterproof sanitary silicone
  • Seal contact points between sanitaryware and walls/floor
  • Wipe excess before it cures
  • Leave silicone to cure 24 hours before using fixtures

6. Post-Installation Checks

Checklist Item What to Check
Flush Operation Strong flow, no leakage from joints
Water Seal Depth (WC) 50–75 mm visible water in bowl trap
Fixing Stability No rocking or movement in installed fixtures
Glaze Cleaning Remove adhesive or tape marks gently
Trap Odor Check Ensure proper U-bend seal and air trap